1. Compensable delivery delay
Acquisitions of new real estate or “ on plans » are legally regulated by the Construction and Housing Code. The sale of a building in a future state of completion (VEFA) and the sale of individual houses (CCMI) are the most common methods of acquiring a new property.
In each of these contracts, the law requires that the delivery time be specified in the act of acquisition. In general, the contract provides for a formula such as “ no later than March 31, 2021 " Or " at the end of the first quarter of 2021 ".
Once this date has passed, the purchaser is entitled to obtain compensation.
However, in most new building sales contracts, in VEFA or CCMI, a clause is provided in which the legitimate reasons for suspension of the delivery period are listed.
The causes given are generally the following:
Severe weather
Third party appeals relating to building permits
Partial or general strike, abandonment of site of a bankrupt company, Covid-19 health crisis
Delays from subsurface anomalies
As long as the delay in delivery of the property is caused by a legitimate and justified cause, no compensation is due from the promoter.
Note that most contracts provide for the addition of a clause which has the effect of doubling the number of days of justified delay and which is worded as follows:
" in the event of the occurrence of one of the events mentioned, this would have the effect of delaying delivery of the goods sold for a time equal to double that actually recorded, due to the repercussion on the general organization of the site "
The Court of Cassation, consistently, considers that this clause is not abusive to the detriment of the non-professional or the consumer because it does not provide a significant imbalance between the rights and obligations of the parties to the contract. [1].
However, if certain causes are legitimate, the developer or builder of the individual house must still justify their existence and their causal link with the delivery delay.
If the manufacturer does not justify the delay in delivery with supporting documents, it is up to the purchaser to send him a formal notice by registered mail to provide him with the supporting documents.
For his part, the purchaser must take care to analyze all the supporting documents given and, if necessary, contest them. This analysis phase can be complex and tedious. The assistance of a lawyer familiar with this type of litigation is recommended in order to obtain the best compensation possible.
2. Compensation in the event of delay in delivery
- Individual House Construction Contract (CCMI) : The standard penalty is at least 1/3000th of the total construction price per day of delay.
- Sale in the future state of completion (VEFA) : Current legislation does not provide specific rules for compensation in the event of delay
3. Obtaining Compensation for Late Delivery
When a delay in the delivery of real estate occurs, the buyer has rights that he can assert. If the developer or builder cites legitimate causes to justify this delay, the purchaser must carry out a verification of the facts and, if necessary, issue a formal notice to claim his damages.
It is strongly recommended to consult a avocat expert en contentieux immobilier to obtain specific advice on the damages likely to be compensated, in particular because moral damage remains complex to quantify.
The option of an amicable settlement is often possible. In this context, a settlement agreement may be concluded between the parties, specifying the terms of compensation, including the period covered and the amounts awarded.
In the absence of an amicable resolution, taking legal action becomes essential to assert your rights to compensation.
Maître Zakine: Your Legal Partner in VEFA, available in person or by Videoconference
Investir dans une Vente en État Futur d’Achèvement (VEFA) est une démarche complexe nécessitant une expertise juridique pointue. Maître Zakine, avocat expert en property law and in particular in terms of VEFA, offers you personalized support to secure your investment and meet your specific needs.
Multidimensional Expertise:
Maître Zakine assists you in a variety of disputes relating to VEFA, including but not limited to:
- Delivery delays and contractual implications
- Tax issues and the impact of Covid-19
- Construction defects and implementation of legal guarantees
- Compliance of the area delivered
- Responsibility of the different actors (promoter, notary, etc.)
Flexibility and Accessibility:
Aware that each client has different constraints and preferences, Maître Zakine offers the possibility of face-to-face consultations in his office or via videoconference. This flexibility allows you to benefit from a high level of legal service.

Frequently asked questions
What are the deadlines to claim late payment penalties in off-plan?
Penalties run from the delivery date stipulated in the contract. You must claim them by registered letter as soon as the delay is noted. For legal action, the limitation period is 5 years from the actual delivery.
Can I obtain compensation for late delivery if the developer invokes bad weather?
Yes, but only if the bad weather is exceptional and unforeseeable. The developer must prove that the delay is due to legitimate causes. A lawyer will check the validity of suspension clauses in your contract.
How much does a lawsuit for late delivery of a VEFA cost?
Lawyer fees can range from €2,000 to €5,000 depending on complexity. Some lawyers offer contingency fees. Do not hesitate to request a quote.
What to do if the developer refuses to compensate for the delay?
You must first put the developer on notice by registered letter. In the absence of a response, you can take the matter to the judicial court. A lawyer will assist you in the procedure and negotiation.
What is a legitimate suspension clause in a VEFA contract?
This is a clause that allows the developer to suspend the delivery deadline in the event of events beyond its control (bad weather, strikes, third-party appeals, etc.). These clauses are strictly interpreted by the courts.

